New Connection of MEPCO Meter

Applying for a new connection of mepco electricity meter is a simple and straightforward process. You can easily submit your application online and track its status in just a few steps.

In this article, we will provide a detailed, step-by-step guide on how to apply for a new MEPCO connection.

If you already have a MEPCO connection and want to check your latest bill, click MEPCO BILL ONLINE.

new connection of mepco meter

New Connection Procedure:

To apply for a new MEPCO connection, follow these steps:

  1. Fill the online form – Apply Here
  2. Find the Apply button on leftside of your PC screen
  3. Select your company name – MEPCO
  4. Select your subdivision – (e.g., Multan Cantt)
  5. Select category type – (e.g., 15KW)
  6. Enter your neighbor’s meter reference number
  7. Select connection type – Domestic, Commercial, Industrial, etc.
  8. Fill your personal information
  9. Notify the number of meters already registered under your name

Required Documents for new meter Application;

To complete your online application, upload the following documents

  1. Property Document Copy – Upload Image
  2. Attested CNIC Copy of Applicant – Upload Image
  3. Attested CNIC Copy of Witness – Upload Image
  4. Neighbor’s Electricity Bill Copy – Upload Image
  5. Wiring Contractor’s Test Report
  6. Next Steps After Form Submission
  7. Print all submitted documents and prepare a file.
  8. Submit the file to your MEPCO subdivision office.
  9. MEPCO will verify your application and conduct a site survey.
  10. After survey approval, a demand notice will be issued.
  11. Print the demand notice, attach the test report, and submit it to the bank with the required fee.

Next Steps After online Form Submission

  1. Print all submitted documents and prepare a file.
  2. Submit the file to your MEPCO subdivision office.
  3. MEPCO officer will verify your application and conduct a site survey.
  4. After survey approval, a demand notice will be issued.
  5. Print the demand notice, attach the test report, and submit it to the bank with the required fee.

If you need any assistance during the application process, visit MEPCO HELPLINE for support.

MEPCO New Connection Demand Notice Fee [ march 2025 ]

The demand notice fee for a new MEPCO connection is diffence of location wise. The charges differ for rural and urban areas:

  • Rural Areas: Approximately PKR 10,000 to 12,000 for a domestic meter.
  • Urban Areas: Ranges from PKR 15,000 to 25,000, with higher fees in well-known societies.

The exact fee depends on the location and MEPCO’s official tariff structure. Visit Mepco office for further detail of new meter demand notice fee in 2025.

How to check new connection application status

Once your demand notice is paid, you can track the status of your MEPCO new connection using your CNIC or the reference number provided in the demand notice.

Track Your Application Here
On this page you see track button on top left corner on your screen.
Here is two options for tracking one is CNIC and sencod is tracking id ( Your 14-digit reference number is your track id)

Check Your New / old MEPCO WAPDA Connection Bill Here

Estimated Time for MEPCO New Meter Installation

The processing time for a new MEPCO connection depends on the category and may take longer than expected. MEPCO categorizes new connections based on load capacity:

Category 1 (Up to 15 kW) – Estimated Timeframe

Category 1 is ideal for domestic and small commercial users, such as houses, small shops, and offices. Below is the estimated timeline for the entire process:

StepsProcedureDays
1Fill out the online application form (ENC) and attach all required documents.1 day
2Print the submitted documents, prepare a file, and submit it to the MEPCO subdivision office for approval.1 day
3Once your application is approved, the concerned officer will verify documents and schedule a site survey.4 days
4After the survey is completed, MEPCO will process your application and generate the new connection demand notice.4 days
5Once processing is done, you will receive an SMS notification stating: “Your Demand Notice 2025 is ready. Please print and pay at the bank.”1 day
6Obtain a wiring test report and attach it to the paid demand notice.1 day
7After payment, you can track your application status.20–30 days
8Issuance of the connection order.5 days
9The MEPCO storekeeper arranges your meter.10 days
10Final step: Meter installation at your premises.1 day

Total Estimated Time: 48 Days

Note: Timelines may vary based on location, workload, and verification processes.

Category-2 (16kw to 70 kws/400 volts)

The process for obtaining a Category-2 MEPCO connection is almost the same as Category-1. However, due to additional verification and processing steps, it may take up to 68 days to complete the installation.

Category-3 (71kW to 500kW / 400 Volts)

Similar to Category-1 and Category-2, the process for obtaining a Category-3 MEPCO connection follows the same steps. However, due to the higher load capacity and additional approvals, the installation process may take up to 100 days from the date of application submission.

  1. How can I apply for a new MEPCO connection online?

    You can apply for a new MEPCO connection by filling out the online application form available on the official website. Ensure you have all the required documents before submission.

  2. What are the charges for a new MEPCO electricity meter in 2025?

    The new meter connection charges vary based on location and category. For a domestic meter, the demand notice fee is approximately PKR 10,000 – 12,000 in rural areas and PKR 15,000 – 25,000 in urban areas.

  3. How can I check my MEPCO new meter connection application status?

    You can track your new connection application status online using your CNIC or reference number allotted on the demand notice.

  4. What is the estimated time for a new MEPCO meter installation?

    The estimated time for a new connection depends on the category:
    Category 1 (Up to 15kW) – 48 days
    Category 2 (16kW to 70kW) – 68 days
    Category 3 (71kW to 500kW / 400V) – 100 days

  5. What documents are required for a new MEPCO meter connection?

    To apply for a new MEPCO electricity connection, you need:
    1. Property document copy
    2. Attested CNIC copy of the applicant
    3. Attested CNIC copy of a witness
    4. Neighbor’s electricity bill copy
    5. Wiring contractor’s test report

  6. How can I download the MEPCO new meter connection demand notice?

    After your application is approved, MEPCO will issue a demand notice. You will receive an SMS notification, and you can download and print the notice online.

  7. Where should I submit my MEPCO new meter connection application?

    After completing the online application, print all submitted documents and submit them to the MEPCO subdivision office for further processing.

  8. Can I check my MEPCO new connection bill online?

    Yes, if you have a new connection, you can check your MEPCO bill online by entering your reference number on the official website.

  9. How can I pay my MEPCO new connection demand notice?

    Once your demand notice is issued, you can pay it at a bank along with the wiring contractor’s test report for further processing.

  10. What is the helpline for MEPCO new connection inquiries?

    If you need assistance regarding your new connection application, tracking status, or billing issues, visit the MEPCO helpline page for support.